The process of bringing a well to completion is generally short-lived, taking a few months for a single well, after which the well can be in production for 20 to 40 years. The process for a single horizontal well typically includes four to eight weeks to prepare the site for drilling, four or five weeks of rig work, including casing and cementing and moving all associated auxiliary equipment off the well site before fracking operations commence, and two to five days for the entire multi-stage fracturing operation.